Design documents in this record are not artifacts produced after the fact. They are the mechanism by which a design is reviewed, argued over and approved, and their revision numbers are the evidence.
The Duval County Courthouse network design ran to 262 pages at revision 16 by the time it was executed. The consolidated CAD/911 dispatch design carried through thirty-five revisions and a review with the Florida Department of Law Enforcement. The enterprise Palo Alto firewall architecture reached twenty-six revisions over its life. The Annex data center consolidation ran on three documents at revisions ten, twelve and ten, each with its own drawing set, test plan and back-out plan.
The overview of the data center consolidation stated plainly that redundancy would be reduced for a period, and what was being done about it. A design document that hides its own risk is worth less than no document.
Subtopics
- AutoCAD & MicroStationWhere the career began — and the tool used decades later to plot wireless coverage heat maps by hand.
Applied in
- Enterprise Agreement Pursuit — Global AutomotiveCisco services subject-matter expert on a bid for a global automotive manufacturer's North American arm — a two-day clarification window, an affiliate's engineering bench as the differentiator, a loss, and a headquarters meeting four weeks later.
- Modernizing Legacy Industrial Systems with AIAn unsupported industrial application whose analysis was still right and whose reference data was not — rebuilt from its inputs, without altering a line of its code.
- Career Reference Record — Design, Build and Publishing PlatformA cross-linked reference work built as a derived graph: edges declared once, every index, backlink and chart generated from them, published static with per-document access control.
- Enterprise Architecture Practice BuildAn architecture practice of up to fourteen, built and run to a design review gate and a weekly rhythm — so engagements were delivered against one design language rather than individual preference.
- Casino Surveillance Network Design and SegmentationSurveillance refresh and segmentation for a metropolitan casino property — designed as Principal Architect and governed as Director, through a phased implementation and a mid-program re-scope.
- Client Architecture Portfolio88 numbered engagements across two years, twenty-plus live at any moment, across healthcare, manufacturing, financial services and the public sector — the inverse of nineteen years inside one estate, and a different problem.
- Multi-Property Gaming GroupFour properties for a regional casino group — security and segmentation, core refresh, wireless, surveillance separation and firewall consolidation.
- Diversified Industrial ManufacturerBusiness-unit and data center assessments, automated discovery and network assurance, an enterprise architecture review, and integration across two acquisitions.
- Network Orchestration Proof of ConceptItential and Gluware assessed against traditional automation for the group's parent company — built out on virtualized topologies rather than judged on datasheets, under a signed statement of work, closing with a master services agreement.
- Enterprise Networking Practice LabThree repurposed servers being rebuilt into a 2.3 TB virtualized network emulation cluster, funded on a cost-per-month argument against a six-month procurement lead time — and the end of a practice running on engineers' own hardware.
- SD-WAN Portfolio — Banking and State LegislatureThree concurrent SD-WAN engagements in regulated and public environments, with the low-level design at revision 2.0 and every configuration passing a routing review before production.
- State and Local Government DeliveryA state transportation department data center relocation inside a single summer window, and county switching, firewall and platform replacement alongside it.
- Commercial Site Rebuild and Live Domain MigrationTwenty pages moved off a hosted page builder onto a static build, and a live domain repointed to a new host without touching any of the six records carrying its mail.
- Municipal Infrastructure Assessment to RFPAn infrastructure assessment for a town government, scoped from the start to become the foundation of its own procurement rather than a proposal for follow-on work.
- Architecture by InfluenceA CIO's instruction — manage by influence rather than by headcount — and the fourteen years of practice built on it, in an estate where nothing could be mandated anyway.
- Consolidated CAD/911 Dispatch SystemTwo agencies with separate commands onto one dispatch platform, cutting response times from five to ten minutes down to one to two.
- Citywide Network Total Cost of Ownership StudyA weighted scoring instrument for a manufacturer standard ahead of a refresh — which earned itself within three weeks, when a reseller's savings claim turned out to be priced against the wrong baseline.
- Main Data Center Physical Connection LayoutThe as-built record of every port, patch and strand in the main data center — a naming convention where the identifier is the location, carried to revision 21 over fifteen years.
- Ed Ball Hearing Room — Backup Council ChambersA committee room specified to run a City Council meeting if the Chamber were unavailable — which makes it a continuity facility for the legislative body, not a meeting room.
- Enterprise Architecture ProgramThe EA practice itself — business, information, technical and solution viewpoints, with strategy, assessments and multi-year capability roadmaps for a platform shared by agencies that answered to different elected officers.
- Enterprise Multi-Tenant Firewall ArchitectureSix independently governed agencies on shared infrastructure, none able to reach, disrupt or inherit the regulatory exposure of any other.
- Electronic Paper Tablet Assessment and RolloutA personal device that became a supported city endpoint — after the enterprise web filtering estate I had built turned out to be the thing breaking it.
- Reliability Engineering PracticeA reliability toolchain bought for one utility engagement in 2000, carried into a city estate, and still running twenty-three years later — availability as a computed number rather than a drawn assertion.
- Requirements or Findings: When Architecture Gets CalledThe same function with the same authority produces requirements on one capital program and findings on another — and the only variable is whether the project called it before or after the build.
- Enterprise Packet Capture and Network Forensics PlatformFull packet capture on eight critical-path points, owned across thirteen years and two platform generations, with retention pushed past thirty days.
- Architecture Technology Governance CommitteeThe second governance body, and the one where architecture decisions were actually worked — with the operations and delivery teams in the room rather than only architects.
- E911 Caller Location and Backup Answering PointMaking the dispatcher see a room instead of a phone number — then building a second answering point so the dispatch center was not a single point of failure.
- Disaster Recovery Validation and Application TieringCriticality bound to recovery objectives in an instrument rather than a narrative, and a definition of "tested" that the estate could not yet meet — reported rather than softened.
- Annex to Main Data Center ConsolidationMoving one data center into another with the estate live throughout, on three design documents at revisions ten, twelve and ten.
- St. James Building WirelessBuilding-wide wireless for City Hall, specified as a measurable coverage floor with heat maps as acceptance and the remediation cost carried by whoever promised the number.
- Enterprise Change Management StandardA change process designed for a utility in 1999, carried into the City as its enterprise standard, and handed to operations in 2012 — after which it outlasted both commercial platforms bought to run it.
- Duval County Courthouse Technology ProgramA $12M IT program inside a $350M, 800,000 square foot capital facility, cut over live to a fixed date.
- Enterprise Security Committee and Governance ProgramThe city's enterprise architecture review board, chaired and chartered — and, in the years before the City had a Chief Security Officer, the body where security policy was set.
- Internet Perimeter Firewall ReplacementAn unsupported, undocumented Check Point estate replaced with firewall blades in the core — held as a stated performance objective, carried from written justification to floor-by-floor cutover, with no vendor producing a design at any point.
- Insurance Carrier E-Commerce PlatformMainframe to public web in 2001, across a colocation tunnel and two firewalls — where the deliverable was the boundary, not the website, and the documentation reached revision 243.
- National Insurance Carrier Enterprise WANFive sites joined over an AT&T frame relay cloud at committed rates from 32K to 320K — an era when the design had to decide what mattered, because not everything could.
Through subtopics
2 further projects reference a subtopic of this entry rather than the entry itself.
- Nassau County Sheriff's Office Countywide WirelessMulti-tower public safety wireless across a large rural county, surveyed by driving it and plotting the readings by hand.
- CSX Railroad Map DigitizationDigitizing CSX property maps dating back to the 1800s, with MDL application development against MicroStation.
Career
- Director of Services · Principal Architect · NRI North America (formerly Core BTS)
- Senior Enterprise Architect · Chief Technology Officer · City of Jacksonville
Documents
- Consolidated Dispatch CJI Boundary DesignThe criminal justice information boundary through the CAD/911 platform, reviewed with the Florida Department of Law Enforcement across thirty-five revisions.
- Enterprise Multi-Tenant Firewall ArchitectureTwenty-six revisions over its life. Palo Alto Networks asked repeatedly to publish it as a vendor white paper; the answer was no every time.
- Duval County Courthouse Network Design262 pages at revision 16 by the time it was executed — the document a live court relocation to a fixed date ran on.